Gas Connection Processing Timeline 2026

Understanding the timeline helps you plan accordingly:

1

Application Submission: Day 1

Submit application with documents at the office

2

Document Verification: Days 2-5

Office staff verify documents for completeness

3

Site Survey: Days 6-15

Surveyor visits property for feasibility assessment

4

Approval: Days 16-20

Approval letter issued with cost estimate

5

Payment & Scheduling: Days 21-30

Pay deposit and charges, schedule installation

6

Installation: Days 31-60

Meter installation and safety inspection

Total Timeline: 30-60 days for standard residential connections. Remote or complex installations may take longer. Commercial connections may take 60-90 days.